The City of Edinburgh Council have released information and updates on roadworks which will be taking place around Wester Hailes over the next few weeks.
Here is some of the information of the works, the disruption they are causing and when they will end taken from the Council website. You can visit the site to find out more information about roadworks across the City.
Murrayburn Road
At Hailesland Road (west junction)
City of Edinburgh Council – installation of signalised pedestrian crossing
Temporary traffic lights 15 – 16/12/23 for signal head installation, anti-skid surfacing and line marking.
21/09/23 – 20/12/23
Hailesland Road
Between Clovenstone Road and Hailesland Park
City of Edinburgh Council – carriageway resurfacing Temporary traffic lights
11/12/23 – 14/12/23
Clovenstone Drive
At the bus stance parallel to Wester Hailes Road
Scottish Water – manhole repair Road closed
19/12/23 – 19/12/23
Clovenstone Gardens
North east corner near Clovenstone House
Last Mile Electricity – cable connections Temporary traffic lights
15/02/24 12/02/24
Calder Road
Between (and including) Bankhead roundabout and Sighthill roundabout City of Edinburgh Council – carriageway resurfacing. All work to be carried out overnight (6.30pm – 6am) on
weekdays only, no work planned during December
W/C 20/11/23 – road closed from Longstone roundabout to Sighthill roundabout and Sighthill Avenue closed.
From 24/11/23 for 5 weekday nights – road closed eastbound from Bankhead roundabout to Longstone roundabout and Broomhouse Road closed
23/10/23 – February 2024